Part 1 – Project Charter: At the end of week two, you are to create and submit the project charter. This is the first official document to be reviewed and approved by the project sponsor. The project charter will include the following components:
· Project title – this is the title of the project
· Purpose – notes why this project is occurring
· Description – what will occur (specifically) in this project
· Objective – the goals you hope to accomplish with this project
· Success criteria or expected benefits – what your outcomes will be (measurable)
· Funding – how will the project be paid for
· Acceptance criteria – what are the things the sponsor is looking for to accept the project
· Major deliverables – what are the key milestone deliverables
· Milestone schedule – calendar dates for Major Deliverable listed above.
· Key assumptions – what are some key things you can assume for this project?
· Constraints/risks – potential obstacles to consider during the project that must be accounted for
· Approval requirements – who approves the project and any changes?
· Reporting requirements – what is reports, how frequently, and by whom?
· Project manager – who is the PM?
· Sponsor designee – who is ultimately responsible (name and title)
Part 2
Scope and Schedule: At the end of week 4, you are to finalize the initially approved scope from week two and start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Structure (WBS). Project scope and schedule will include the following components:
– Finalized project scope – WBS structure – Develop project schedule – Identify key milestones and deliverables – Outline project resources and assign them to tasks accordingly. – Stakeholder engagement – communication plan
Part 3
Budget and Risk Management: At the end of this week, you are to finalize the overall project cost and clearly document project risks gathered throughout the project. As part of the risk management plan, you are expected to share a risk response plan. Project cost and risk management plans will include the following components:
– Overall project budget (utilizing EVM – share current and forecasted project status) – Project requirements – Cost management plan – outlining contingency plan for project changes – Risk management matrix – Change management process – Project RAID (Risk, The assumption, Issues, and Dependencies)
Part 4
Final week, you are to finalize the overall project management plan (PMP) and to integrate all previously submitted components incorporated with instructor (project sponsor) feedback into a single project management plan. The project management plan will include the following components:
– Project quality management plan to include an updated scope, cost, schedule, communication, risk, resources, procurement, and quality) – Project requirements – updated – Stakeholder register – updated – How project RAID (Risk, Assumption, Issues, and Dependencies)will be managed – Project sponsor approval of the key project deliverables